Notes on maps Ground Implementation
DLS implementation: planned status – February 2018 notes
- Bulgaria: Only SITA coverage – no FOC date;
- Cyprus: Implementation expected by Dec 2018
- Estonia: Implementation delayed to March 2018 (Only SITA coverage)
- Finland: Only SITA coverage expected by 12/2018 – NO FOC date
- France: IOC implemented (DLIC, ACM, AMC); ACL implementation Brest and Bordeaux: 12/2018, Reims and Marseille: 11/2020, Paris: 11/2022 (new ATM system)
- Greece: Preliminary planning started – no FOC date
- Italy: Padua ACC implementation Feb 2018; Milan ACC April 2018; Rome ACC March 2018;
- Latvia: Only SITA coverage – delay in ATM upgrade – FOC end 2018
- Lithuania: implementation by Q3 2019 (Vilnius FIR – new ATM system)
- Malta: Implementation will start shortly – no FOC date
- Norway: Implementation expected by Q2 2021 (new ATM system)
- Poland: DLS deployment: March 2018 reaching SITA and ARINC network users
- Portugal: IOC implemented (DLIC) – only SITA – no FOC date
- Romania: only SITA coverage – Implementation expected Q4 2018 (new ATM system) – No FOC date
- Slovakia: Implementation expected by end 2020 – no SITA and ARINC coverage – no ATM upgrade
- Slovenia: implementation expected by December 2018 (no ARINC coverage and no ATM upgrade)
- Spain: Barcelona and Canarias only SITA coverage; Madrid by May 2018
DLS implementation: planned status – May 2018 notes
- Bulgaria: only SITA coverage – no FOC date
- Cyprus: Implementation expected by Dec 2018
- Estonia: Only SITA coverage – no FOC date
- Finland: Only SITA coverage expected by 12/2018 – NO FOC date
- France: IOC implemented (DLIC, ACM, AMC); ACL implementation Brest and Bordeaux: Dec 2018, Reims and Marseille: Nov 2020, Paris: Nov 2022 (new ATM system)
- Greece: Preliminary planning started – no FOC date
- Latvia: Only SITA coverage – delay in ATM upgrade – FOC end 2018
- Lithuania: implementation by Q3 2019 (Vilnius FIR – new ATM system)
- Malta: Implementation will start shortly – no FOC date
- Norway: Implementation expected by Q2 2021 (new ATM system)
- Portugal: IOC implemented (DLIC) – only SITA – no FOC date
- Romania: only SITA coverage – Implementation expected Q4 2018 (new ATM system) – No FOC date
- Slovakia: Implementation expected by end 2020 – no SITA and ARINC coverage – no ATM upgrade
- Slovenia: implementation expected by December 2018 (no ARINC coverage and no ATM upgrade)
DLS implementation: planned status – December 2018 notes
- Bulgaria: only SITA (no ARINC coverage) – no FOC date
- Estonia: Only SITA coverage – no FOC date
- Finland: only SITA coverage – NO FOC date
- France: only IOC implemented (DLIC, ACM, AMC) in Reims, Marseille and Paris; ACL implementation Reims and Marseille: Nov 2020, Paris: Nov 2022 (new ATM system)
- Greece: Preliminary planning started – no FOC date
- Lithuania: implementation by Q3 2019 (Vilnius FIR – new ATM system)
- Malta: Partial implementation expected – no FOC date
- Norway: Implementation expected by Q2 2021 (new ATM system)
- Portugal: IOC implemented (DLIC) – SITA and ARINC coverage – no FOC date
- Romania: only SITA coverage – Implementation (expected) Q4 2018 – No FOC date
- Slovakia: Implementation expected by end 2020 – no SITA and ARINC coverage – no ATM upgrade